Referenzliste
2 / 3
Windpark Tüngeda-Oesterbehringen, Thüringen
begin / 06/2015 | power / 6.600 kW |
completion / 12/2015 |
close
99820 Tüngeda-Oesterbehringen / Thüringen
start of building:
06/2015
installation:
12/2015
Thüringen
Windpark Tüngeda-Oesterbehringen
location: | 99820 Tüngeda-Oesterbehringen / Thüringen |
start of building: | 06/2015 |
installation: | 12/2015 |
power: | 6.600 kW |
supply of 4-pers. households: | 3.500 |
plant type: | 2x Vestas V126 - 137 |
Windpark Tüngeda-Oesterbehringen
location:99820 Tüngeda-Oesterbehringen / Thüringen
start of building:
06/2015
installation:
12/2015
Windpark Lindau II, Thüringen
begin / 10/2014 | power / 2.500 kW |
completion / 03/2015 |
close
07613 Lindau / Thüringen
start of building:
10/2014
installation:
03/2015
Thüringen
Windpark Lindau II
location: | 07613 Lindau / Thüringen |
start of building: | 10/2014 |
installation: | 03/2015 |
power: | 2.500 kW |
supply of 4-pers. households: | 1.600 |
plant type: | 1 x Nordex N100 - 100 |
Windpark Lindau II
location:07613 Lindau / Thüringen
start of building:
10/2014
installation:
03/2015
Windpark Rauschwitz III, Thüringen
begin / 12/2013 | power / 3.000 kW |
completion / 06/2014 |
close
07616 Rauschwitz / Thüringen
start of building:
12/2013
installation:
06/2014
Thüringen
Windpark Rauschwitz III
location: | 07616 Rauschwitz / Thüringen |
start of building: | 12/2013 |
installation: | 06/2014 |
power: | 3.000 kW |
supply of 4-pers. households: | 2.340 |
plant type: | 1 x Nordex N117 - 120 |
Windpark Rauschwitz III
location:07616 Rauschwitz / Thüringen
start of building:
12/2013
installation:
06/2014
Windpark Wetzdorf, Thüringen
begin / 03/2013 | power / 19.200 kW |
completion / 12/2013 |
close
07619 Wetzdorf / Thüringen
start of building:
03/2013
installation:
12/2013
Thüringen
Windpark Wetzdorf
location: | 07619 Wetzdorf / Thüringen |
start of building: | 03/2013 |
installation: | 12/2013 |
power: | 19.200 kW |
supply of 4-pers. households: | 16.550 |
plant type: | 8 x Nordex N117 - 141 |
Windpark Wetzdorf
location:07619 Wetzdorf / Thüringen
start of building:
03/2013
installation:
12/2013
Windpark Lindau, Thüringen
begin / 03/2013 | power / 15.000 kW |
completion / 07/2013 |
close
87613 Lindau / Thüringen
start of building:
03/2013
installation:
07/2013
Thüringen
Windpark Lindau
location: | 87613 Lindau / Thüringen |
start of building: | 03/2013 |
installation: | 07/2013 |
power: | 15.000 kW |
supply of 4-pers. households: | 9.700 |
plant type: | 6 x Nordex N100 - 100 |
Windpark Lindau
location:87613 Lindau / Thüringen
start of building:
03/2013
installation:
07/2013
Windpark Bucha, Thüringen
begin / 08/2012 | power / 2.500 kW |
completion / 12/2013 |
close
07751 Bucha / Thüringen
start of building:
08/2012
installation:
12/2013
Thüringen
Windpark Bucha
location: | 07751 Bucha / Thüringen |
start of building: | 08/2012 |
installation: | 12/2013 |
power: | 2.500 kW |
supply of 4-pers. households: | 1.370 |
plant type: | 1 x Nordex N100 - 100 |
Windpark Bucha
location:07751 Bucha / Thüringen
start of building:
08/2012
installation:
12/2013
Windpark Zschöpel, Thüringen
begin / 07/2011 | power / 10.250 kW |
completion / 11/2011 |
close
04639 Zschöpel / Thüringen
start of building:
07/2011
installation:
11/2011
Thüringen
Windpark Zschöpel
location: | 04639 Zschöpel / Thüringen |
start of building: | 07/2011 |
installation: | 11/2011 |
power: | 10.250 kW |
supply of 4-pers. households: | 5.940 |
plant type: | 5 x REpower MM 92 - 100 |
Windpark Zschöpel
location:04639 Zschöpel / Thüringen
start of building:
07/2011
installation:
11/2011
Windpark Rauschwitz II, Thüringen
begin / 07/2010 | power / 4.100 kW |
completion / 03/2011 |
close
07616 Rauschwitz / Thüringen
start of building:
07/2010
installation:
03/2011
Thüringen
Windpark Rauschwitz II
location: | 07616 Rauschwitz / Thüringen |
start of building: | 07/2010 |
installation: | 03/2011 |
power: | 4.100 kW |
supply of 4-pers. households: | 3.690 |
plant type: | 2 x Repower MM92 |
Windpark Rauschwitz II
location:07616 Rauschwitz / Thüringen
start of building:
07/2010
installation:
03/2011
Windpark Rackwitz, Sachsen
begin / 09/2006 | power / 3.000 kW |
completion / 11/2006 |
close
04519 Rackwitz / Sachsen
start of building:
09/2006
installation:
11/2006
Sachsen
Windpark Rackwitz
location: | 04519 Rackwitz / Sachsen |
start of building: | 09/2006 |
installation: | 11/2006 |
power: | 3.000 kW |
supply of 4-pers. households: | 2.700 |
plant type: | 2 x Nordex S70 |
Windpark Rackwitz
location:04519 Rackwitz / Sachsen
start of building:
09/2006
installation:
11/2006
Windpark Hörningen, Thüringen
begin / 01/2001 | power / 4.000 kW |
completion / 08/2006 |
close
99734 Hörningen / Thüringen
start of building:
01/2001
installation:
08/2006
Thüringen
Windpark Hörningen
location: | 99734 Hörningen / Thüringen |
start of building: | 01/2001 |
installation: | 08/2006 |
power: | 4.000 kW |
supply of 4-pers. households: | 3.600 |
plant type: | 2 x Enercon E 58, 1 x REpower MM82 |
Windpark Hörningen
location:99734 Hörningen / Thüringen
start of building:
01/2001
installation:
08/2006