Windpark Tüngeda-Oesterbehringen, Thüringen
begin / 06/2015 power / 6.600 kW
completion / 12/2015
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Tüngeda-Oesterbehringen

location:99820 Tüngeda-Oesterbehringen / Thüringen
start of building:06/2015
installation:12/2015
power: 6.600 kW
supply of 4-pers. households:3.500
plant type:2x Vestas V126 - 137

Windpark Tüngeda-Oesterbehringen

location:
99820 Tüngeda-Oesterbehringen / Thüringen
start of building:
06/2015
installation:
12/2015
Windpark Lindau II, Thüringen
begin / 10/2014 power / 2.500 kW
completion / 03/2015
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Lindau II

location:07613 Lindau / Thüringen
start of building:10/2014
installation:03/2015
power: 2.500 kW
supply of 4-pers. households:1.600
plant type:1 x Nordex N100 - 100

Windpark Lindau II

location:
07613 Lindau / Thüringen
start of building:
10/2014
installation:
03/2015
Windpark Rauschwitz III, Thüringen
begin / 12/2013 power / 3.000 kW
completion / 06/2014
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Rauschwitz III

location:07616 Rauschwitz / Thüringen
start of building:12/2013
installation:06/2014
power: 3.000 kW
supply of 4-pers. households:2.340
plant type:1 x Nordex N117 - 120

Windpark Rauschwitz III

location:
07616 Rauschwitz / Thüringen
start of building:
12/2013
installation:
06/2014
Windpark Wetzdorf, Thüringen
begin / 03/2013 power / 19.200 kW
completion / 12/2013
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Wetzdorf

location:07619 Wetzdorf / Thüringen
start of building:03/2013
installation:12/2013
power: 19.200 kW
supply of 4-pers. households:16.550
plant type:8 x Nordex N117 - 141

Windpark Wetzdorf

location:
07619 Wetzdorf / Thüringen
start of building:
03/2013
installation:
12/2013
Windpark Lindau, Thüringen
begin / 03/2013 power / 15.000 kW
completion / 07/2013
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Lindau

location:87613 Lindau / Thüringen
start of building:03/2013
installation:07/2013
power: 15.000 kW
supply of 4-pers. households:9.700
plant type:6 x Nordex N100 - 100

Windpark Lindau

location:
87613 Lindau / Thüringen
start of building:
03/2013
installation:
07/2013
Windpark Bucha, Thüringen
begin / 08/2012 power / 2.500 kW
completion / 12/2013
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Bucha

location:07751 Bucha / Thüringen
start of building:08/2012
installation:12/2013
power: 2.500 kW
supply of 4-pers. households:1.370
plant type:1 x Nordex N100 - 100

Windpark Bucha

location:
07751 Bucha / Thüringen
start of building:
08/2012
installation:
12/2013
Windpark Zschöpel, Thüringen
begin / 07/2011 power / 10.250 kW
completion / 11/2011
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Zschöpel

location:04639 Zschöpel / Thüringen
start of building:07/2011
installation:11/2011
power: 10.250 kW
supply of 4-pers. households:5.940
plant type:5 x REpower MM 92 - 100

Windpark Zschöpel

location:
04639 Zschöpel / Thüringen
start of building:
07/2011
installation:
11/2011
Windpark Rauschwitz II, Thüringen
begin / 07/2010 power / 4.100 kW
completion / 03/2011
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Rauschwitz II

location:07616 Rauschwitz / Thüringen
start of building:07/2010
installation:03/2011
power: 4.100 kW
supply of 4-pers. households:3.690
plant type:2 x Repower MM92

Windpark Rauschwitz II

location:
07616 Rauschwitz / Thüringen
start of building:
07/2010
installation:
03/2011
Windpark Rackwitz, Sachsen
begin / 09/2006 power / 3.000 kW
completion / 11/2006
close
chevron_left
chevron_right
fullscreen

Sachsen

Windpark Rackwitz

location:04519 Rackwitz / Sachsen
start of building:09/2006
installation:11/2006
power: 3.000 kW
supply of 4-pers. households:2.700
plant type:2 x Nordex S70

Windpark Rackwitz

location:
04519 Rackwitz / Sachsen
start of building:
09/2006
installation:
11/2006
Windpark Hörningen, Thüringen
begin / 01/2001 power / 4.000 kW
completion / 08/2006
close
chevron_left
chevron_right
fullscreen

Thüringen

Windpark Hörningen

location:99734 Hörningen / Thüringen
start of building:01/2001
installation:08/2006
power: 4.000 kW
supply of 4-pers. households:3.600
plant type:2 x Enercon E 58, 1 x REpower MM82

Windpark Hörningen

location:
99734 Hörningen / Thüringen
start of building:
01/2001
installation:
08/2006